Tuesday, June 30, 2009

We have a new file organization structure and I am so happy about it.

Thursday, June 25, 2009

Site clearing











While I was working on the knotweed our contractor, DIGS, was taking
care of the big stuff. We have to eliminate all of the invasive species
(which is the bulk of vegetation on the site) to qualify for LEED points.

Hopefully the next step is clearing the mosquitoes off of the site.

Invasive patrol

I decimated Japanese knotweed this morning. I used cut shrub & vine killer which was so nasty that afterwards I couldn't even wash my clothes in my own washing machine because we have a septic tank and it could get into the groundwater. After reading the directions completely I don't think I'll ever be able to make myself buy it again. Once I'm out I think I'll use roundup for 2-3 treatments instead.

Would you live in this module?


Goings-on at Milton
















I took these shots Tuesday after I got tired of being a Cad-monkey in the office with Edric and Alison (right).

Tuesday, June 23, 2009

Blog Update


Our blog look has been updated thanks to Jen!

Friday, June 19, 2009

High Schoolers


We have had a nice group of high schoolers volunteering this week helping things move along a bit more quickly.

Wednesday, June 17, 2009

Ductwork


Ductwork was installed!

Tuesday, June 16, 2009

Sitework

Our contractor, DIGS INC, will start clearing and excavating this week. I am busy figuring out the erosion control logistics. Look for pictures Thursday or Friday.

Putting up Drywall on the first floor module!


Wednesday, June 3, 2009

MOD2 Wall 1

The first wall for the upper module has gone vertical. The second wall goes up tomorrow. Great job mod2 framing team.


Monday, June 1, 2009