carpenter's log: build date 09/25

quick update:

Cory is painting some cabinetry and starting to clad MOD1.




James is continuing with window trim.




Leslie is putting down flooring paper in MOD1 to get ready for our bamboo flooring tutorial.




Quarles is driving to a wedding, but probably thinking about cabinets and shading devices.


I
am blocking out all external outlets, vents, and light fixtures.




-Graham



Wednesday, September 23, 2009

carpenter's log: build date 09/23

Perakis is busy working on some of the trim inside mod01.
Caldwell is slaving away on the cement fiber board siding.
Peterson is finishing up on some flashing and furring for mod01.
McDonald is leading us in the right direction.
I just finished some cabinetry in the stair mod.

tbc. . .

-quarles

Sunday, September 20, 2009

Sunday, September 13, 2009